Project Process

Listed below is the entire basement egress window system process when working with us.
  • Customer sends images of the interior & exterior of their basement
  • Initial quote sent via text & email
  • Customer accepts contract & pays deposit
  • Site visit scheduled & 1/2 project cost collected
  • Permit package created & submitted
  • Utility mark-out scheduled before installation
  • Installation scheduled once permit is received
  • Materials delivered prior to installation
  • Typical installations are a 1-2 day process
  • On project completion the total project cost is due
  • Final inspection scheduled

*Project process may vary depending on the exact site conditions & chosen materials